A Review of the Decision in Modilim vs. United Bank for Africa Plc
by Cajetan Osisioma
Introduction
On 19th June 2014, Justice B. B. Kanyip of the National Industrial Court of Nigeria, sitting in
Lagos, delivered a well-considered judgment in Mr. Patrick Obiora Modilim vs. United
Bank for Africa Plc2, where the claimant sought, among other reliefs, a declaration that the
defendant’s failure to upgrade and/or review the claimant’s emoluments to that of a general
manager’s level amounted to a breach of his contract of employment and a declaration that
the defendant constructively and wrongfully terminated the claimant’s employment.
Summary of Facts of the Case
The claimant was offered employment by the defendant as a Deputy General Manager and
the defendant undertook to confirm his appointment as a General Manager after a period of
six months subject only to the condition that the claimant would meet certain set targets
contained in a performance contract executed by the parties. The claimant contended that
he met the set targets and was confirmed but that the defendant continued to pay him the
salaries of a Deputy General Manager for the 20 months he worked after his confirmation
despite repeated demands by the claimant that his employment be reviewed to that of a
General Manager. Consequently, the claimant was forced to resign his employment via a
letter of resignation dated 31st March 2010 and the defendant purportedly accepted the
claimant’s resignation via a letter dated 30th March 2010. The claimant contended that the
totality of the defendant’s attitude clearly showed that he was constructively dismissed. The
defendant, however, maintained that the claimant voluntarily resigned his appointment, did
not work as a General Manager and therefore cannot be paid salaries of a General
Manager.
Decision of the Court
In its judgment, the court held, inter alia, that the defendant’s failure to review the claimant’s
level to that of a General Manager on confirmation was a breach of his contract of
employment contained in the offer letter and letter of commitment, thereby holding the
defendant liable to the claimant for breach of its commitment.
Loss of Expectation Interest and Claim thereof
The decision in this case is important as it touches on a novel area of the law which is not
yet fully appreciated in Nigeria and other jurisdictions; that is, loss of expectation interests
and claim thereof. In upholding part of the claimant’s relief, the court held as follows:
“Having therefore breached the contract of employment and so entitling the
claimant to relief (b) as indicated, the next question is what the remedy of the
claimant is. The commitment on the part of the defendant to be willing to review
the claimant’s position to the level of General Manager gave rise to an expectation
interest on the part of the claimant. The rule, by Tadduggoronno v. Gotom [2002]
NWLR (Pt. 757) 453, is that there cannot be a vested right when an exercise is
made subject to the fulfillment of some conditions and acceptance of those
conditions at the discretion of the affirming body. And in Medical and Health
Workers Union of Nigeria & Ors v. Federal Ministry of Health unreported Suit No.
NICN/ABJ/238/2012, the judgment of which was delivered on July 22, 2013, this
Court acknowledged that the practice of skipping of salary grade levels by
Government can create an expectation interest, which in turn is capable of
creating an entitlement or vested right in favour of the complainants who have all
this while been beneficiaries of the practice. In the instant case, the conditions for
the exercise of the commitment on the part of the defendant were all met. In fact,
in University of Jos v. Dr. M. C. Ikegwuoha [2013] 9 NWLR (Pt. 1360) 478, the
Supreme Court ordered that the respondent’s appointment be confirmed once the
conditions for confirmation were met. In the instant case, the claimant is no longer
in the service of the defendant, so the question of ordering that he be confirmed
does not arise. The claimant in the instant case is accordingly entitled to a remedy
regarding the loss of the expectation interest in terms of the breach of the
defendant’s commitment to be willing to review his position to the level of General
Manager”.
Further, the Court queried: “What then is the measure of damages for this loss of expectation
interest?” And, after its computation and determination of the difference in salaries between
the Deputy General Manager and that of the General Manager, awarded the sum of
N75,535,128.00 as the measure of damages in expectation interest that the claimant would
have earned had the defendant kept to its commitment to review the employment of the
claimant from the position of a Deputy General Manager to that of a General Manager upon
confirmation as agreed.
Comments
The Court was right in holding that the defendant was in breach of its commitment to be
willing to review the claimant’s position to the level of General Manager upon confirmation
and that the breach gave rise to an expectation interest on the part of the claimant. Judges
involved in labour/employment law disputes are encouraged to be proactive in granting
claims for expectation interests where the facts and circumstances of cases reveal (as in the
case under review) that certain benefits would have accrued to a claimant had the defendant
kept to its commitment as contained in a contract of employment.
1 Cajetan Osisioma is an Associate with S. P. A. Ajibade & Co., Lagos, Nigeria: +234 (0) 8063640152,
cosisioma@spaajibade.com
2 Suit No. NICN/LA/353/2012